Nima Paloma Drainage Works Await Finance Ministry Approval
Story By: Deborah Adorsu
The Ministry of Works, Housing and Water Resources is awaiting commitment authorisation from the Finance Ministry to repackage the Nima-Paloma drainage works under the GARID Project for a new contract.
This follows the termination of the previous contract over poor performance.
Minister Ahmed Ibrahim provided an update on the project’s progress and work completed in Parliament.
The project involves the construction of a 1.5-kilometre box culvert from Nima-Paloma to the Odaw River.
It started in July 2024 and was to be completed within 18 months.At the time of termination, progress on major construction components was below 10 per cent.
Excavation works had reached 13 per cent, while demolition of the existing drain stood at 25 per cent.
Casting of concrete beds and walls recorded 9.7 per cent and 9.5 per cent progress respectively.
The Nima-Paloma drainage upgrade forms part of the Greater Accra Resilient and Integrated Development (GARID) Project, a World Bank-supported programme aimed at improving flood risk management, drainage infrastructure and urban resilience in Greater Accra.